Larson Creek Trail Segment II: Ellendale to Black Oak (Connect Oregon V Program) (STP653 530)

December 2017:
Public Works is working with engineering consultant, ZCS Engineering, to prepare construction drawings for two pedestrian path bridge crossings along the proposed trail. Preliminary bridge plans are expected for review by end of January 2018. Right-of-way acquisition activities continue along with overall plan preparation. The project is scheduled to be advertised for bids summer 2018.

March 2018:
Engineering consultant, ZCS Engineering, has received preliminary review comments for the two pedestrian path bridge crossings along the proposed trail. ZCS Engineering will work to produce a 90% bridge design and submit for review. Engineering consultant, Brown and Caldwell, is performing a flood study as needed to obtain a flood development permit for the project. Right-of-way acquisition activities continue as does overall plan preparation (currently at 60%). This project is scheduled to be advertised for bids summer 2018.

July 2018:
Engineering Consultant, ZCS Engineering, has submitted 90% bridge design for review.  Engineering consultant, Brown and Caldwell, has completed a No-rise Certification as needed to obtain a flood development permit for the project. Right-of-way acquisition activities continue as does overall plan preparation (currently at 80%). This project is scheduled to be advertised for bids summer 2018.  

October 2018:
Public Works is working on final plans and is tentatively scheduled to go to bid November 2018. Environmental permitting is complete and acquisition of right-of-way is nearly done. Bridge plans are being finalized and project constructability is being analyzed. Overall, project construction scheduled to be completed October 2019.

December 2018:
Public Works completed the construction plans, advertised for bids, and opened bids on December 13, 2018. JRT Construction, LLC submitted the lowest responsible bid of $1,756,202.35. Seven (7) bids were received with one removed from consideration and deemed non-responsive. The contract is scheduled to go to City Council for approval on Thursday, January 17, 2019.

March 2019:
JRT Construction, LLC, scheduled to start work on the project site the second week of April, weather permitting. First activities will be clearing and grubbing and removal and placement of fencing. Project completion scheduled for November 2019.

 
Larson Creek Trail map
 
July 2019:
JRT Construction LLC, has constructed approximately 45% of the project with retaining walls and bridge abutments being the current focus. The 80 foot and 100 foot long pedestrian bridges are being fabricated and project is scheduled to be complete November 2019.

M653

STP0653

October 2019:
JRT Construction is nearly finished. Completion of path striping, signing, and minor fencing are the only items that remain. Final inspection with City Staff is scheduled the second week of October. Anticipated completion date is October 18, 2019.

December 2019:
JRT Construction has completed the project and its currently opened to the public. ​

STP0653

March 2020:
Project is constructed and waiting a final inspection by ODOT staff following relaxation of COVID-19 provisions.

June 2020:
Project has been inspected by City of Medford and ODOT staff.  Currently waiting for written confirmation of final approval and acceptance.
 

Project Details

Start Date:
4/19/2019
Completion Date:
10/19/2019
Project Status:
Completed
Contact Name:
Public Works Engineering
Contact Phone:
(541) 774-2100
Contact Email:

© 2020 City Of Medford  •  Site Handcrafted in Ashland, Oregon by Project A

Quicklinks

Share This Page

Back to Top