ADA Ramp Construction Schedule, February 12-20

Public Works News (View All)

ADA Ramp Construction Schedule, February 12-20

Please note that crews from Brown Contracting, Inc. will be performing ADA ramp construction work at the following location.  Lane closures are possible but not likely.  Flaggers will be in place if needed.  Work will be performed between the hours of 7:00 a.m. and 6:00 p.m.  No work will take place on weekends or holidays.

February 12-20: 
Sherman Street - from Hawthorne St. to Stark St.

Travelers should expect delays associated with this work and are advised to seek alternate routes and parking. We appreciate your patience and cooperation in keeping Medford's work zones safe. Weather conditions or equipment failures may delay the above schedule.


City of Medford
Public Works Operations
541.774.2600
 