Sewer System Repair Work Schedule, March 19-23

Public Works News (View All)

Sewer System Repair Work Schedule, March 19-23

Please note that crews from Michels Corporation will be performing sewer collection system repair work at the following locations.  There will be lane closures with flaggers in place.  No work will take place on weekends or holidays.
March 19-23, 7:00 a.m. - 6:00 p.m.
  • Bennet Ave. - from Howard Ave. to west end
  • Edwards St. - from Beatty St. to Niantic St.
  • Kenwood Ave. - from Sunset Ave. to Locust St.
  • Alley - between E 3rd St and E 4th St, west of N Bartlett St.
Travelers should expect delays associated with this work and are advised to seek alternate routes and parking. We appreciate your patience and cooperation in keeping Medford's work zones safe. Weather conditions or equipment failures may delay the above schedule.

City of Medford
Public Works Operations

© 2018 City Of Medford  •  Site By Project A